Leading the substantial permit variation to increase the capacity of plasterboard manufacturing at Etex’s existing site in Bristol.
CLIENT:
Etex Building Performance
LOCATION:
Bristol
SERVICES:
- Permitting
- Air quality
- Noise
- Site condition
OUR APPROACH & DELIVERABLES
Etex was aiming to make a substantial investment in its existing plasterboard manufacturing facility in Bristol which would result in an approximate doubling of capacity.
Logika led pre-application consultation with the Environment Agency on behalf of Etex that confirmed that a substantial variation to its existing permit would be required due to the scale of the expansion.
Logika then developed the full suite of documents, plans and associated assessments that supported the variation application including BAT assessments, air quality assessment, noise assessment and an updated site condition report. Logika also managed all post submission consultation and responses to further information requests from the Environment Agency. Due to strategy adopted during pre-application consultation, these further information requests were limited in their scope, allowing timely determination of the varied permit.